OSF Hospital, Peoria, IL |
|
| |
|
|
 |
| |
|
|
| |
Johnson HVAC crews will, by May 2010, complete more than 90,000 labor hours on the fabrication and installation of air handling systems within the OSF Hospital addition in Peoria, IL.
Supervising as many as 56 tradesmen primarily from the local community, JCC crews will install more than 1.2 million pounds of ductwork, much of it fabricated within our extensive facilities and shipped to Peoria in 250 truckloads.
Completion of the 465,000-square foot, $5 million project required use of the latest computer modeling technology, as well as the coordination with seven other building trades simultaneously working the job.
 |
| |
| Steve Cutts |
| Senior MAP Engineer, Mortenson Construction talks about JCC at OSF. |
| Play Video |
|
| |
| |
|
|
|
|
| |
|
|
| |
|
|
|
 |
| |
|
|
| |
Gimmie Shelter:
John Deere Aviation Hanger |
|
| |
|
|
 |
| |
|
|
| |
When Deere & Company, headquartered in Moline, IL wanted to assure a comfortable environment for workers and protective space their substantial investment in corporate aircraft, they called on the HVAC experts at JCC to craft the airflow system within their new hanger.
Completed in March 2010, the new facility equally divides its 62,500 sq. ft. between aircraft storage & maintenance and attractively appointed areas devoted to a reception/waiting and business offices for pilots and mechanics.
In total JCC invested more than 2180 hours in this fabrication and installation project.
| |
Project |
John Deere Aviation Hanger |
| |
Customer |
Deere & Company |
| |
Dimensions |
4,600 lineal feet of duct |
| |
Weight |
32,800 # |
| |
Man Hours |
1,339 Field Hours and
841 Shop Hours |
|
|
|
|
| |
|
|
| |
|
|
|
|
|
|
 |
|